Timeline

Original Planning Timescales for Phase 1

  • Submission of Proposal of Application Notice April 2013
  • Public Events – July-13
  • Submission of Planning Application – October 2013
  • Submission of Scheme 2 Application – January 2014
  • Scheme Re-Advertisement – January 2014
  • Planning approval received – March 2014
  • Outline Business Case approval – October 2014
  • Financial Close –October 2014
  • Building work to start on site – November 2014.
  • Phase one project completion – late 2016. (Actual completion took place in 2017)

Planning timescales for Phase 2  & 3 are still being agreed. This page will be updated in due course.